Gordie Howe International Bridge

Client

Bridging North America (BNA)

Owner

Windsor–Detroit Bridge Authority (WDBA) 

Location

Detroit, MI

about

  • Designed and developed the erection sequence for the curved approach spans, which consisted of 10 girders, 9 spans, and nearly 1800ft of total bridge length.
  • Engineered pier brackets to be installed at pier locations to facilitate girder erection.
  • Developed picking and rigging plans for all 140 girders.

Services Provided

Falsework, Geometry Control, Highway Bridges, Temporary Work

Completion

2025

Other Projects

Hawk Falls Bridge

Portal North Bridge Erection 

Belden G. Bly Bridge Replacement

MDOT S10 Bridge Deck Removal

Hawk Falls Bridge

Portal North Bridge Erection 

Belden G. Bly Bridge Replacement

Buck O’Neil Bridge Replacement

Hawk Falls Bridge

Portal North Bridge Erection 

Belden G. Bly Bridge Replacement

Buck O’Neil Bridge Replacement

Hawk Falls Bridge

Portal North Bridge Erection 

MDOT S10 Bridge Deck Removal

Buck O’Neil Bridge Replacement

Hawk Falls Bridge

Portal North Bridge Erection 

Belden G. Bly Bridge Replacement

Buck O’Neil Bridge Replacement