about
- Staged analysis for arch erection on temporary falsework at an offsite marine facility
- Designed strut system to allow arch to be picked up with SPMT’s
- Designed roll-on procedure to roll SPMT’s onto a deck barge
- Designed heavy lift jacking barge
- Designed longitudinally slid system to slide bridge 100ft to the final bearing locations
Services Provided
Bridge Float-In/Float-Out, Cable Supported Bridges, Falsework, Geometry Control, Heavy Civil, Highway Bridges, Railroad Bridge, Specialty Rigging, Temporary Construction Bridge, Temporary Shoring Bridge, Temporary Work
Completion
2026